[Dec-2021 Newly Released] AACE-PSP Exam Questions For You To Pass
AACE International AACE-PSP Exam: Basic Questions With Answers
What is the duration, language, and format of the Planning & Scheduling Professional (PSP) Exam
- Passing score: 70%
- Total questions: 119
- Language of Exam: English
- Format: Multiple choice, compound, scenario questions + 1 memo writing assignment
- Duration of Exam: 5 hours
How to book the Planning & Scheduling Professional (PSP) Exam
Follow the steps mentioned below to book the Planning & Scheduling Professional (PSP) Exam:
- Step 1: Visit the AACE’s website by clicking here
- Step 2: Create a new account or log in to an existing account
- Step 3: Select your professional exam
- Step 4: Complete the required course and take PSP practice test
- Step 5: Fill the application and submit all required documents
- Step 6: Schedule your exam by following the instructions on the website
For more info read reference:
NEW QUESTION 53
Is activity 7001 pictured correctly in the precedence diagram?
- A. No, the start-to-start and finish-to-finish relationships are backwards.
- B. Yes, the duration is 48 days.
- C. No, the total float is not shown correctly.
- D. Yes, except the early finish date is not shown.
Answer: B
NEW QUESTION 54
The expected remaining cost needed to complete an activity, group of activities or the project is the____________.
- A. Estimate to complete (ETC)
- B. Estimate at completion (EAC)
- C. Budget at completion (BAC)
- D. Budgeted cost of work performed (BCWP)
Answer: A
NEW QUESTION 55
What is the cycle time?
- A. 14 minutes
- B. 5 minutes
- C. 6 minutes
- D. 17 minutes
Answer: D
NEW QUESTION 56
What is the primary difference between the arrow diagramming method (ADM) and the precedence diagramming method (PDM)?
- A. ADM is limited to finish-to-start logic relationships, while PDM is not.
- B. PDM is a bar chart with network logic, while ADM is a pure logic network.
- C. ADM uses arrows, while PDM uses boxes.
- D. ADM is manual CPM calculations, while PDM is computerized.
Answer: A
NEW QUESTION 57
An early start constraint dictates
- A. The planned start of a successor activity
- B. The planned start of an activity.
- C. An activity's remaining duration.
- D. The actual start of an activity.
Answer: A
NEW QUESTION 58
The work breakdown structure is used to organize
- A. Similar activity coding of schedule activities
- B. The chart of accounts
- C. "Smart activity ID codes" representing similar items of scheduled work
- D. The smallest defined work packet
Answer: D
NEW QUESTION 59
The linear scheduling velocity diagram has the following two-axis:
- A. Time and rate of progress
- B. Time and location
- C. Location and crew size
- D. Time and crew size
Answer: A
NEW QUESTION 60
Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?
- A. 8 work days
- B. 7 work days
- C. 18 work days
- D. 15 workdays
Answer: A
NEW QUESTION 61
At a minimum, periodic reporting must be done at what interval?
- A. Monthly.
- B. As requested by the project manager.
- C. As requested by the owner.
- D. As specified in the contract documents.
Answer: D
NEW QUESTION 62
Which activity is drawn in the incorrect position?
- A. Activity C.
- B. Activity D.
- C. Activity G.
- D. Activity E.
Answer: B
NEW QUESTION 63
How much Total Float does drafting the product manual have?
- A. 10 workdays.
- B. 15 workdays.
- C. 0 workdays.
- D. 5 workdays.
Answer: A
NEW QUESTION 64
Time-scaled logic diagrams are
- A. Logic networks that are drawn to match the calendar.
- B. Only calculated using a computer.
- C. The same as a pure-logic diagram.
- D. Used to calculate the most probable activity duration.
Answer: A
NEW QUESTION 65
What does the narrow band at "Y" represent?
- A. A rework period.
- B. You cannot tell with the information supplied.
- C. Resource limitation period.
- D. Activity inactivity.
Answer: D
NEW QUESTION 66
Which of the following is NOT required when initially planning a project?
- A. Logical relationships between the tasks.
- B. A schedule that identifies tasks required on a project.
- C. Resource Identification and leveling.
- D. The duration of each task.
Answer: D
NEW QUESTION 67
There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?
- A. 2 cranes
- B. 3 cranes
- C. 4 cranes
- D. 1 crane
Answer: A
NEW QUESTION 68
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):
- A. The delay must affect the contractor's planned construction schedule.
- B. The delay must not cause monetary harm to the defendant.
- C. The delay must affect the critical path.
- D. The delay must be concurrent with the delay attributable to both parties.
Answer: C
NEW QUESTION 69
Budgeted cost of work scheduled is _______________________.
- A. The value of the completed work expressed in terms of the budget assigned to that work
- B. The total authorized budget for accomplishing the project scope
- C. The sum of all budgets for work scheduled to be accomplished within a given time period
- D. The expected total cost of an activity, group of activities or the project
Answer: D
NEW QUESTION 70
How could the structural steel drawing delay have been prevented?
- A. Release the structural steel for fabrication concurrent with review of structural steel shop drawings.
- B. Allow adequate time for review and resubmittal in the baseline schedule.
- C. Switch to post-tensioned concrete construction.
- D. Add a time buffer at the end of structural steel activities.
Answer: D
NEW QUESTION 71
......