Guide (New 2022) Actual PRINCE2 PRINCE2-Foundation Exam Questions
PRINCE2-Foundation Exam Dumps Pass with Updated 2022 Certified Exam Questions
How to study the PR2F Exam
There are two main types of resources for preparation of certification exams first there are the study guides and the books that are detailed and suitable for building knowledge from ground up then there are video tutorial and lectures that can somehow ease the pain of through study and are comparatively less boring for some candidates yet these demand time and concentration from the learner. Smart Candidates who want to build a solid foundation in all exam topics and related technologies usually combine video lectures with study guides to reap the benefits of both but there is one crucial preparation tool as often overlooked by most candidates the practice exams. Practice exams are built to make students comfortable with the real exam environment. Statistics have shown that most students fail not due to that preparation but due to exam anxiety the fear of the unknown. Exams4sures expert team recommends you to prepare some notes on these topics along with it don’t forget to practice Exin PR2F dumps which been written by our expert team, Both these will help you a lot to clear this exam with good marks.
PRINCE2 PRINCE2-Foundation Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
NEW QUESTION 112
Which should be provided by corporate or programme management before the Starting up a Project process commences?
- A. A Project Brief
- B. The Project Initiation Documentation
- C. Sufficient information to identify the prospective Executive
- D. Authority to initiate a project
Answer: C
Explanation:
Section: Volume B
NEW QUESTION 113
What product identifies the management stages and other major control points in a project?
- A. Work Package
- B. Project Brief
- C. Project Plan
- D. Business Case
Answer: C
NEW QUESTION 114
What is an advantage of applying the 'learn from experience' principle?
- A. It allows the project team to fully understand their roles and responsibilities
- B. It allows the project manager to delegate time tolerances to the team managers
- C. It allows the project board to delegate cost tolerances to the project manager
- D. It allows the project team to identify improvements to be made during the project
Answer: D
Explanation:
Section: Volume B
Explanation/Reference:
NEW QUESTION 115
Which is a step in the recommended approach to 'defining and analyzing the products'?
- A. Identifying activities and dependencies
- B. Designing a plan
- C. Preparing estimates
- D. Writing a project product description
Answer: B
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Plans
NEW QUESTION 116
Which is a minimum requirement for applying the change theme?
- A. To produce a breakdown of the products to be produced
- B. To ensure each change is managed as an exception
- C. To identify whether an issue affects the continuation of the project
- D. To tailor all changes to improve the quality of the project
Answer: B
Explanation:
Section: Volume B
NEW QUESTION 117
How does the project board use the 'manage by stages' principle to control the project?
- A. By reviewing project viability at defined intervals
- B. By ensuring that the benefits are managed and controlled
- C. By approving the project management team
- D. By reviewing previous project closure documentation
Answer: A
Explanation:
Explanation
Reference http://prince2.wiki/Manage_by_stages
NEW QUESTION 118
Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?
- A. Starting up a Project
- B. Initiating a Project
- C. Managing a Stage Boundary
- D. Managing Product Delivery
Answer: A
Explanation:
Section: Volume B
NEW QUESTION 119
Which PRINCE2 principle is being applied when tolerances are set to establish limits of authority and accountability?
- A. Continued business justification
- B. Manage by stages
- C. Manage by exception
- D. Defined roles and responsibilities
Answer: C
Explanation:
Explanation/Reference:
Reference http://prince2.wiki/Manage_by_exception
NEW QUESTION 120
Which of the following statements about the Closing a Project process are true?
1. The Closing a Project process provides a fixed point for the receipt of completed Work
Packages for the work performed in the final stage.
2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved. Packages for the work performed in the final stage.
- A. Only 2 is true
- B. Both 1 and 2 aretrue
- C. Neither 1 or 2 are true
- D. Only 1 is true
Answer: A
NEW QUESTION 121
Which is a purpose of the quality theme?
- A. To identify all the products of the project to ensure the scope has been adequately defined
- B. To establish baselines against which any changes to products can be assessed
- C. To determine the communication needs of the organization's quality assurance function
- D. To establish how the project will ensure that all products created meet their requirements
Answer: D
NEW QUESTION 122
Which theme provides all management levels within the project management team with mechanisms for monitoring and control?
- A. Progress
- B. Quality
- C. Change
- D. Organization
Answer: A
Explanation:
Explanation
Reference https://www.whatisprince2.net/prince2-theme-progress.php
NEW QUESTION 123
When considering risks, which describes an opportunity in a project?
- A. An uncertain event that could have a favourable impact on objectives
- B. An event that has occurred resulting in a favourable impact on objectives
- C. An event that has occurred resulting in a negative impact on objectives
- D. An uncertain event that could have a negative impact on objectives
Answer: A
NEW QUESTION 124
What must a PRINCE2 project demonstrate?
- A. Application of the activities in each process
- B. Application of tools appropriate for the industry
- C. Application of proper leadership skills
- D. Application of PRINCE2 principles
Answer: D
Explanation:
Section: Volume B
NEW QUESTION 125
Which are benefits of using PRINCE2?
1. It removes the need for activity-based planning
2. It promotes learning and continuous improvement
3. It can be applied to any type of project
4. It defines specific leadership and other interpersonal skills required
- A. 1 and 2
- B. 1 and 4
- C. 2 and 3
- D. 3 and 4
Answer: C
Explanation:
Explanation/Reference:
Reference https://www.axelos.com/best-practice-solutions/prince2/key-benefits-of-prince2
NEW QUESTION 126
What is the collective name for individuals or groups who may be affected by a project?
- A. Stakeholders
- B. Team members
- C. Customers
- D. Project Support
Answer: A
NEW QUESTION 127
Which role is responsible for the management of a risk assigned to it?
- A. Project Assurance
- B. Risk owner
- C. Project Support
- D. Risk actionee
Answer: B
NEW QUESTION 128
When considering risks, which describes an opportunity in a project?
- A. An uncertain event that could have a favourable impact on objectives
- B. An event that has occurred resulting in a favourable impact on objectives
- C. An event that has occurred resulting in a negative impact on objectives
- D. An uncertain event that couldhave a negative impact on objectives
Answer: A
NEW QUESTION 129
Why is a Project Brief produced?
- A. To act as a trigger for the Starting up a Project process
- B. To record the strategies and management controls to be used by a project
- C. To be used by the Project Board as a basis for reviewing the progress of a project
- D. To provide a full and firm foundation for the initiation of a project
Answer: D
NEW QUESTION 130
Which is a minimum requirement for applying the organization theme?
- A. The roles of the project management team must be combined, wherever possible
- B. The project manager must be appointed from the supplier organization
- C. Each member of the project management team must have a written role description
- D. The frequency of communication to the project's stakeholders must be documented
Answer: D
Explanation:
Explanation
Reference
http://prince2.wiki/Themes#Organization_Theme
NEW QUESTION 131
If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?
- A. Senior User
- B. Executive
- C. Corporate/programme management
- D. Senior Supplier
Answer: C
NEW QUESTION 132
Which is a purpose of an End Project Report?
- A. Identify individuals or groups that need to be told that the project is coming to an end
- B. Review how well the project performed against the Project Initiation Documentation used to authorize it
- C. Ensure that key project information is archived and made secure
- D. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
Answer: B
NEW QUESTION 133
......
Pass Guaranteed Quiz 2022 Realistic Verified Free PRINCE2: https://www.exams4sures.com/PRINCE2/PRINCE2-Foundation-practice-exam-dumps.html