NEW QUESTION 95
Which is an objective of the Starting up a Project process?
- A. Confirm that there is a validmethod in place to measure the expected project benefits
- B. Approve allProduct Descriptions prior to project initiation
- C. Prevent projects with unrealistic delivery dates from being initiated
- D. Obtain approval from corporate or programme management for the Communication
Management Strategy
Answer: C
NEW QUESTION 96
In what product should the quality criteria for a specialist product be recorded?
- A. Quality Management Strategy
- B. Product Description
- C. Quality Register
- D. Project Product Description
Answer: B
NEW QUESTION 97
Which is a purpose of the Quality theme?
- A. Establish how the project will ensure that all products created meet their requirements
- B. Identify all the products of the project to ensure the scope has been adequately defined
- C. Determine the communication needs of the organization's quality assurance function
- D. Establish quality assurance to maintain the quality management system
Answer: A
NEW QUESTION 98
Which does the Executive need to ensure is in place before the project is initiated?
- A. An understanding of how the project will contribute to corporate objectives
- B. All Work Packages are authorized
- C. The Project Plan has been approved
- D. The Project Initiation Documentation is complete
Answer: A
NEW QUESTION 99
What must be produced to meet the minimum requirements when applying the change theme?
- A. Records of the decisions made on all issues
- B. Documents recording the version of each product
- C. A change budget for the analysis of change
- D. Status reports on all products being produced
Answer: A
Explanation:
Section: Volume B
NEW QUESTION 100
Where should an off-specification be recorded?
- A. Issue Register
- B. Configuration Management Strategy
- C. Work Package
- D. Risk Register
Answer: A
NEW QUESTION 101
From whom does a Team Manager obtain approval for a completed product?
- A. The authoritydefined in the Product Description
- B. Senior Supplier
- C. Project Support
- D. Project Manager
Answer: A
NEW QUESTION 102
Which is a purpose of an Exception Plan?
- A. Define the changes which are within the scope of the change budget
- B. Reduce the number of exception assessments, by agreeing a budget to cover the costs of any requests for change
- C. Show the reason for the tolerance deviation from a Stage Plan or Project Plan
- D. Identify the actions required to recover from the effect ofa tolerance deviation
Answer: D
NEW QUESTION 103
Identify the missing word(s) in the following sentence. Quality assurance provides assurance to the [?] that the project is being conducted appropriately whilst Project Assurance provides the same assurance to all the project's stakeholders,
- A. corporate or programme management organization
- B. Executive
- C. Supplier groups
- D. Project Manager
Answer: A
NEW QUESTION 104
Which is an objective of the quality review technique?
- A. To ensure that staff are properly trained in the quality methods
- B. To assess that a product conforms to set criteria
- C. To provide assurance that the project is being conducted properly
- D. To identify a product's quality criteria
Answer: B
NEW QUESTION 105
Which is NOT a purpose of the Initiating a Project process?
- A. Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved
- B. Enable the Project Board to decide whether it is worthwhile to initiate a project
- C. Enable a Project Board decision about the commitment of resources to a project
- D. Establish solid foundations for a project
Answer: B
Explanation:
Section: Volume A
NEW QUESTION 106
How many management stages should a PRINCE2 project consist of?
- A. Initiation stage and at least one other management stage to cover the remainder of the project
- B. Start up stage, initiation stage and a closing stage
- C. Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
- D. Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
Answer: A
Explanation:
Section: Volume B
NEW QUESTION 107
Which is a minimum requirement for applying the risk theme?
- A. Threats must be assessed for their impact on the viability of the project
- B. The PRINCE2 risk management procedure must be followed
- C. Team managers must maintain their own risk registers
- D. A single role that is responsible for all risks must be defined
Answer: A
Explanation:
Section: Volume B
Explanation/Reference:
Reference https://www.prince2primer.com/prince2-2017-risk-theme-changes/
NEW QUESTION 108
What information should be recorded in the quality register?
- A. Potential threats to the project's objectives and how they will be managed
- B. Off-specifications that will occur during the project
- C. Planned activities to determine whether the products are fit for purpose
- D. Lessons that the project will capture and use during the project
Answer: D
Explanation:
Section: Volume B
Explanation/Reference:
Reference https://mplaza.pm/prince2-quality-register-template/
NEW QUESTION 109
Which is a step in the recommended approach to 'defining and analyzing the products'?
- A. Writing a project product description
- B. Preparing estimates
- C. Identifying activities and dependencies
- D. Designing a plan
Answer: D
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Plans
NEW QUESTION 110
Which is a purpose of a quality register?
- A. To record the quality management approach for a product
- B. To detail the number and type of quality activities to be conducted
- C. To identify corrective actions that are required after an audit by quality assurance
- D. To issue a unique reference number for each product
Answer: B
Explanation:
Explanation/Reference:
Reference http://prince2.wiki/Quality#The_Quality_Register