NEW QUESTION 19
Which circuits are on the utility side of a service point?

  • A. Feeders
  • B. Service conductors
  • C. Service lateral
  • D. Service entrance conductors

Answer: B

 

NEW QUESTION 20
A AWG THWN-2 PV output conductors from two PV arrays are run in the same 3 in, conduit to their respective functionally grounded inverters in the building. The three PV source circuits are each protected by a
15A fuse in the combiner box at the array. The conduit, which is strapped directly to the roof,is exposed to design temperatures of 140' F (60'C) during its 30 ft.
Exposed run. What is the MAXIMUM current carrying capability value of the PV output conductors?

  • A. 54A
  • B. 61A
  • C. 34A
  • D. 42A

Answer: C

 

NEW QUESTION 21
When doinginitial inspections on a PV system that was installed using racking that is not compliant with UL.2703, an inspector should pay special attention to which electrical attribute?

  • A. Each PV module needs to be bonded to the equipment grounding conductor.
  • B. The grounding conductor must be bonded directly to the primary grounding electrode.
  • C. Racking needs to be bonded to a supplemental grounding electrode conductor.
  • D. The equipment grounding conductor must be irreversibly spliced.

Answer: A

 

NEW QUESTION 22
Which of the following MUST be referenced for determining a site's design wind speed?

  • A. The jurisdiction's local building code in effect
  • B. The NEC version in effect
  • C. The ASHRAE Handbook_fundamentals in effect
  • D. The module manufacture's design wind speed

Answer: C

 

NEW QUESTION 23
Which electrical connection requires the use of a torque device to complete the connection per NEC requirements?

  • A. Screw terminals on an ac receptacle outlet
  • B. Underground direct-burial twist-on wire connector
  • C. Soldered splices in a conduit body
  • D. Crimp-on log to the battery cable

Answer: D

 

NEW QUESTION 24
A PV connection is being made at the center of a 300 ft. long 200 feeder. See the attack diagram. The feeder originates in the upper third of the 800A main service panel (800A main breaker) with a 200A breaker and terminates in a 200A main-lug-only subpanel. The rated output of the PV system inverter is 100A.

Which are the NIMUMUM actions required to achieve an NEC-compliant installation?

  • A. Install a 200A breaker at the PV source connection point on the portion of the feeder toward the subpanel, maintain the capacity of the entire feeder, and move the 200A breaker to the bottom of the main service panel, away from the 800A main breaker.
  • B. Install a 200A breaker at the PV source connection point on the portion on the portion of the feeder toward the subpanel and move the 200A breaker to the top of the main service panel, adjust to the 800A main breaker.
  • C. Install a 325A breaker at the PV source connection point on the portion of the feeder toward the subpanel. Increase thecapacityof the feeder from the main panel board to 325A breaker to the bottom of the main service panel, away from the 800 main breaker.
  • D. Install a 325A at the PV source connection point on the portion of the feeder toward the subpanel, increase the capacity of this portion of the feeder to 325A, add a 200A main breaker to the subpanel, and move the 200A breaker to bottom of the main service panel, away from the 800A main breaker.

Answer: C

 

NEW QUESTION 25
Which of the following tests measures axial uplift whenperforming load testing of driven-pile foundation members

  • A. Resistance to twisting
  • B. Resistance to horizontal movement
  • C. Resistance to withdraw (pull-out) force
  • D. Resistance to downward (Sinking force

Answer: C

 

NEW QUESTION 26
When installing an ungrounded PV system with an open-circuit voltage of 450Vdc and a maximum voltage of
3000Vdc which procedures should be followed to establish an electrically safe condition?

  • A. Verify that disconnecting device blades are closed and test conductors using an adequately rated detector.
  • B. Mount inverters on nonconductive supports and temporarily ground one dc circuit conductor.
  • C. Determine possible sources electrical supply an avoid exposure to energized conductors or parts.
  • D. Apply lockout/tagout devices and install a listed isolation transformer.

Answer: C

 

NEW QUESTION 27
A technician has been called to a scale due to a low-performing array. The technician will perform tests in the
24-source circuit combiner box. After putting on the correct PPE and turning off and performing lock.tagout of the inverted and combiner disconnect. Which is the next step to safely begin electrical testing in the combiner box?

  • A. Test for voltage on the positive out
  • B. Test for current on each source circuit coming into the combiner box.
  • C. Remove any surge suppression devices from the circuits.
  • D. Open all fuse holders in the combiner box.

Answer: D

 

NEW QUESTION 28
A PV system equipped with rapid shutdown requires a label stating ''RAPID SHUTDOWN SWITCH FOR SOLAR PV SYSTEM''.
Which is the BEST description of where this label is required?

  • A. On or within 3 ft. of the ac disconnect
  • B. On or within 3 ft. of the ac disconnect
  • C. On or within 3 ft. of the ac disconnect
  • D. On or within 3 ft. of the ac disconnect

Answer: D

 

NEW QUESTION 29
An installer is hired to troubleshoot a 10-year-old roottop system with open-circuitvoltage of 300V. The ground-fault detection (GFD) device has tripped. The insulation on the exposed source circuit cables has deterlorated with multiple cracks and has no flexibility. Which concern is the MOST likely safely issue when servicing this array?

  • A. Cracked insulation has allowed water intrusion that resulted in oxidation of the copper conductors.
  • B. Insulation has become an electrical conductor since it has changed its composition.
  • C. Ungrounded conductors are conducing current event the ground-fault device has activated.
  • D. Short-circuit current is present at the PV source-circuit terminals of the disconnect device because of electrical leakage.

Answer: B

 

NEW QUESTION 30
A dwelling has a 200A main load center with a 150 main breaker. Which of the following is the MOST powerful 240V inverter that can be installed in the house using the existing main panelboard with a backfed breaker?

  • A. 7, 689W
  • B. 9, 600W
  • C. 21, 600W
  • D. 17, 280W

Answer: D

 

NEW QUESTION 31
The NEC requires that PV systems installed on dwellings incorporate which of the following components?

  • A. Dc lightning surge arrestors
  • B. A dc ground-fault protect device
  • C. A lockable utility disconnect at the point-of-utility interconnection
  • D. Blocking diodes across each module

Answer: C

 

NEW QUESTION 32
An 8 AWG bare copper equipment ground conductor (EGC) is wire tied to the module mounting structure of a commercial rooftop solararray. After a few years of operation, some spots on the EGC begin to turn a green color and appear to be corroding more significantly that other places. What would the MOST likely cause of the problem?

  • A. Array racking touching the EGC at multiple points
  • B. A break in the EGC, leaving the array ungrounded
  • C. Bypass dlode failures inducing current on the EGC
  • D. Nyton wire ties in contact with the copper wire

Answer: A

 

NEW QUESTION 33
A customer has a 200A service with a 200A rated panel and 200A main breaker located on the street side of the house. There is a 100A breaker located at the opposite end of busbar feeding a 125A subpanel in the backyard. The customer would like to place the inverter the backyard and use the 125 subpanel. Which MAXIMUM inverter(s) output circuit current could be installed?

  • A. 40A
  • B. 32A
  • C. 42A
  • D. 30A

Answer: A

 

NEW QUESTION 34
A PV array with 58 in. X 38 in modules in portrait orientation is to be mounted at a 35 tiit angle on a shingle roof that has a 5:12 pitch. Assuming the support leg is attached to the top of the modules and is perpendicular to its face, what is the length of the support leg for the modules?

  • A. 12.73 in.
  • B. 24.24 in.
  • C. 18.25 in.
  • D. 40.50 in.

Answer: A

 

NEW QUESTION 35
......

Verified PVIP dumps Q&As 100% Pass in First Attempt Guaranteed Updated Dump: https://drive.google.com/open?id=15j6cjeCJnoGG6HVDuBRcoo1Y8EvCIX4z